Answer :
Solution :
UNITS TO ACCOUNT FOR :
[tex]\text{Beginning Work}[/tex] in Process units $ [tex]25,000[/tex]
[tex]\text{Add: Units Started}[/tex] in Process $ [tex]14,000[/tex]
Total Units to account for $ [tex]165,000[/tex]
UNITS TO BE ACCOUNTED FOR:
[tex]\text{Units completed}[/tex] and transferred out $ [tex]135,000[/tex]
[tex]\text{Ending Work}[/tex] in Process $ [tex]30,000[/tex]
[tex]\text{Total Units}[/tex] to be accounted for $ [tex]165,000[/tex]
[tex]\text{Equivalent units}[/tex]
Material cost Conversion
% of completion Units % of completion Units
[tex]\text{Units started}[/tex] [tex]100\%[/tex] $[tex]135,000[/tex] [tex]100\%[/tex] $[tex]135,000[/tex]
and completed.
[tex]\text{Ending Work}[/tex] in Process [tex]100\%[/tex] [tex]30,000[/tex] [tex]30\%[/tex] [tex]9000[/tex]
[tex]\text{Total equivalent units}[/tex] [tex]165,000[/tex] [tex]144,00[/tex]
Therefore, the equivalent units of conversion is [tex]144,000 \text{ units}.[/tex]