Answer :
Answer:
70,438.20
Step-by-step explanation:
To calculate the future value you use the following formula
FV=PV(1+i)^n
Plug in our numbers and get
FV=42000(1+.09)^6
42000*1.09^6=70,438.20
Answer:
70,438.20